Track Your Scheme

Scheme Details
DISTRICT Pilibhit
AGENCY VISHVARAJ
SCHEME ID 20060838
SCHEME NAME ROHANIA + 2 MULTI GRAM PANCHAYAT WATER SUPPLY SCHEME
ESTIMATED COST 527.04
EXPENDITURE 369.87
AUTOMATION STATUS
SCHEME STATUS Trial Run
Scheme Physical Progress
Village Coverage
Village Covered 4
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 37
Procured 37 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 16566.00 Meter
Length Laid 16066.00 Meter

Scheme Assigned Villages

4 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Pilibhit Bisalpur Chathia Sewaram 405200 Chathia Sewaram 273 273 100% Har Ghar Jal Not Certified
2 Pilibhit Bisalpur Chathia Sewaram 405201 Dhimerpura 26 26 100% Har Ghar Jal Not Certified
3 Pilibhit Bisalpur Karmapurmaffi 405253 Karmapur Mafi 201 201 100% Har Ghar Jal Not Certified
4 Pilibhit Bisalpur Rohania 405262 Rohania 448 447 100% Work In Progress Not Certified