Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Pilibhit | VISHVARAJ | 20060922 | MANPUR MARORI + 2 MULTI GP WATER SUPPLY SCHEME | 485.00 | 295.23 | view more | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 37 | 37 | Yes | 0 | NA | No | 16076.00 | 15476.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Pilibhit | Bisalpur | BARSI URF BARSIA | 405212 | BARSI BALEY URF BARSIA | 196 | 188 | 96 | Work In Progress | Not Certified | 
| 2 | Pilibhit | Bisalpur | BARSI URF BARSIA | 405213 | CHAUKHANDI | 148 | 148 | 100 | Har Gar Jal | Not Certified | 
| 3 | Pilibhit | Bisalpur | Daulatpur Heera | 405254 | Daulatpur Heera | 339 | 339 | 100 | Har Gar Jal | Not Certified | 
| 4 | Pilibhit | Bisalpur | Manpur Marori | 405272 | Manpur Marori | 148 | 148 | 100 | Har Gar Jal | Not Certified | 
| 5 | Pilibhit | Bisalpur | Manpur Marori | 405273 | Vedkhera | 137 | 136 | 99 | Work In Progress | Not Certified |