Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Pratapgarh | Power Mech Projects Ltd | 20063235 | RAJAPUR & NAVEDA GAURADAND WATER SUPPLY SCHEME | 457.56 | 260.68 | Verified | Verified | view more |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Pratapgarh | Sandwa Chandrika | Newada Gaura Dand | 429656 | Newada Gaura Dand | 193 | 193 | 100 | Har Gar Jal | Not Certified | Not Verified |
2 | Pratapgarh | Sandwa Chandrika | Newada Gaura Dand | 429657 | Sarai Ugai | 120 | 72 | 60 | Work In Progress | Not Certified | Not Verified |
3 | Pratapgarh | Sandwa Chandrika | Rajapur Rainiya | 429697 | Rajapur Rainiya | 308 | 307 | 100 | Work In Progress | Not Certified | Not Verified |
4 | Pratapgarh | Sandwa Chandrika | Rajapur Rainiya | 429698 | Balapur | 162 | 161 | 99 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
4 | 2 | 2 | 2 | 2 | 1 | 1 | 1 | 39 | 39 | Yes | 0 | NA | No | 27018.00 | 27018.00 |