Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Kanpur Dehat | Indian Hume Pipe | 20064925 | Korai | 258.22 | 91.29 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 0 | 0 | 1 | 0 | 0 | 21 | 21 | NA | 0 | NA | No | 9485.00 | 8068.10 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Kanpur Dehat | Sarvankheda | Korari | 421488 | Chitariya Ikhalaspur | 39 | 38 | 97 | Work In Progress | Not Certified | 
| 2 | Kanpur Dehat | Sarvankheda | Korari | 421489 | Usmanpur Jamrehi | 150 | 95 | 63 | Work In Progress | Not Certified | 
| 3 | Kanpur Dehat | Sarvankheda | Korari | 421490 | Korari | 332 | 316 | 95 | Work In Progress | Not Certified |