Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Etah Power Mech Projects Ltd 20064976 RADHEYNAGAR 353.21 154.30 Not Integrated

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
5 2 2 2 2 1 1 1 36 36 Yes 0 NA No 10422.00 10422.00

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Etah Sakit Radheynagar 399685 Radheynagar 232 228 98 Work In Progress Not Certified
2 Etah Sakit Radheynagar 399686 Kishanpur Kawar 12 11 92 Work In Progress Not Certified
3 Etah Sakit Radheynagar 399687 Sarfuddeen Husainpur 67 66 99 Work In Progress Not Certified
4 Etah Sakit Radheynagar 399688 Bidhee Kheria 49 48 98 Work In Progress Not Certified
5 Etah Sakit Radheynagar 399689 Kadampur 59 58 98 Work In Progress Not Certified