Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Etah | Power Mech Projects Ltd | 20065005 | KASELA SCHEME | 245.81 | 95.20 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Etah | Jaithara | Kasela | 399162 | Kasela | 223 | 94 | 42 | Work In Progress | Not Certified | Not Verified |
2 | Etah | Jaithara | Kasela | 399163 | Sirau | 120 | 29 | 24 | Work In Progress | Not Certified | Not Verified |
3 | Etah | Jaithara | Kasela | 399164 | Slempur | 24 | 1 | 4 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 20 | 20 | Yes | 0 | NA | No | 8759.00 | 8785.00 |