Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Aligarh | PNC-SPML-JV | 20065276 | BHARTRI & RUSTAMPUR DAULA WSS | 392.75 | 151.62 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 30 | 30 | Yes | 0 | NA | No | 17419.00 | 17000.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Aligarh | Lodha | Rustampur Daula | 394499 | Rustampur Daula | 124 | 124 | 100 | Har Gar Jal | Not Certified | 
| 2 | Aligarh | Lodha | Rustampur Daula | 394500 | Sangor | 119 | 119 | 100 | Har Gar Jal | Not Certified | 
| 3 | Aligarh | Lodha | Bhartri | 394507 | Bhartri | 297 | 297 | 100 | Har Gar Jal | Not Certified | 
| 4 | Aligarh | Lodha | Bhartri | 394508 | Hayatpur Bajhera | 194 | 176 | 91 | Work In Progress | Not Certified |