Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Prayagraj | Larsen & Toubro Ltd | 20065739 | Tajpur urf Bhikhanpur-Budauna Multi village water supply scheme | 299.75 | 168.89 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Prayagraj | Kaudihaar | Tajpur Urf Bhikhanpur | 431741 | Tajpur Urf Bhikhampur | 147 | 146 | 99 | Work In Progress | Not Certified | Not Verified |
2 | Prayagraj | Kaudihaar | Budauna | 431750 | Budauna | 433 | 433 | 100 | Har Gar Jal | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
2 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 28 | 28 | Yes | 0 | NA | No | 20036.00 | 20005.00 |