Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Mainpuri | NCC Ltd. | 20066381 | JALALPUR DIKHATMAI + PRAYAGPUR GRAM PANCHAYAT WATER SUPPLY SCHEME | 266.98 | 167.96 | Verified | Verified | view more |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Mainpuri | Bewar | Prayagpur | 400551 | Piyapur | 95 | 93 | 98 | Work In Progress | Not Certified | Not Verified |
2 | Mainpuri | Bewar | Prayagpur | 400552 | Nagla Baal | 47 | 46 | 98 | Work In Progress | Not Certified | Not Verified |
3 | Mainpuri | Bewar | Prayagpur | 400553 | Dikhat Mai | 72 | 71 | 99 | Work In Progress | Not Certified | Not Verified |
4 | Mainpuri | Bewar | Jallalpur Dikhatmai | 400554 | Jalalpur Dikhatmai | 183 | 183 | 100 | Har Gar Jal | Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
4 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 20 | 20 | Yes | 0 | NA | No | 13185.00 | 12950.00 |