Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Gorakhpur | NCC Ltd. | 20066816 | Asthaula & Pichaura of Gagah JJM | 284.67 | 212.38 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Gorakhpur | Gagha | Asthaula | 456513 | Asthaula | 213 | 213 | 100 | Har Gar Jal | Certified | Not Verified |
2 | Gorakhpur | Gagha | Asthaula | 456514 | Sonayeecha | 108 | 108 | 100 | Har Gar Jal | Certified | Not Verified |
3 | Gorakhpur | Gagha | Asthaula | 456515 | Belavir Bhan | 87 | 87 | 100 | Har Gar Jal | Certified | Not Verified |
4 | Gorakhpur | Gagha | Pichhaura Of Gagha | 456519 | Pichhaura | 232 | 232 | 100 | Har Gar Jal | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 30 | 30 | Yes | 0 | NA | No | 8870.00 | 14169.50 |