Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Sultanpur | UNIVERSAL MEP | 20066964 | BHADA & PAKARI GROUP OF GRAM PANCHAYAT WATER SUPPLY SCHEME | 616.42 | 403.58 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Sultanpur | Dubepur | Bhada | 440405 | Bhada | 405 | 403 | 100 | Work In Progress | Not Certified | Not Verified |
2 | Sultanpur | Dubepur | Pakari | 440415 | Pakari | 282 | 282 | 100 | Har Gar Jal | Not Certified | Not Verified |
3 | Sultanpur | Dubepur | Pakari | 440416 | Purejaddu | 105 | 105 | 100 | Har Gar Jal | Certified | Not Verified |
4 | Sultanpur | Dubepur | Pakari | 440417 | Pure Kashiram | 37 | 37 | 100 | Har Gar Jal | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
4 | 2 | 2 | 2 | 2 | 2 | 1 | 2 | 39 | 39 | Yes | 0 | NA | No | 33604.00 | 33604.00 |