Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Sultanpur | UNIVERSAL MEP | 20066973 | NATUALI & SONBARSA GRAM PANCHAYAT WATER SUPPLY SCHEME | 543.29 | 305.01 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 2 | 2 | 2 | 2 | 1 | 1 | 0 | 40 | 40 | Yes | 0 | NA | No | 20298.00 | 19300.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sultanpur | Waldirai | Natauli | 439365 | Natauli | 177 | 161 | 91 | Work In Progress | Not Certified |
| 2 | Sultanpur | Waldirai | Natauli | 439366 | Adampur | 115 | 113 | 98 | Work In Progress | Not Certified |
| 3 | Sultanpur | Waldirai | Natauli | 439367 | Kalyan Pur | 97 | 90 | 93 | Work In Progress | Not Certified |
| 4 | Sultanpur | Waldirai | Sonbarsa | 439368 | Sonbarsa | 270 | 250 | 93 | Work In Progress | Not Certified |