Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Kanpur Dehat | VSA | 20067009 | DURRAJPUR, RATAPUR | 310.77 | 215.61 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Kanpur Dehat | Rajpur | Durrajpur | 421825 | Durrajpur | 189 | 189 | 100 | Har Gar Jal | Certified | Not Verified |
2 | Kanpur Dehat | Rajpur | Durrajpur | 421826 | Mohammadpur Newada | 124 | 124 | 100 | Har Gar Jal | Certified | Not Verified |
3 | Kanpur Dehat | Rajpur | Ratapur | 421838 | Ratapur | 244 | 244 | 100 | Har Gar Jal | Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 37 | 37 | Yes | 0 | NA | No | 9259.00 | 9800.00 |