Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Pilibhit | VISHVARAJ | 20067099 | NAGRA RATA +1MGP Water Supply Scheme | 398.66 | 274.19 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 23 | 23 | Yes | 0 | NA | No | 18544.00 | 17944.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Pilibhit | Bilsanda | Nagra Rata | 405068 | Nagra Rata | 222 | 199 | 90 | Work In Progress | Not Certified |
| 2 | Pilibhit | Bilsanda | Nagra Rata | 405069 | Dhak Riya | 150 | 140 | 93 | Work In Progress | Not Certified |
| 3 | Pilibhit | Bilsanda | Nagariya Tulagiri | 405123 | Nagariya Tulagiri | 224 | 210 | 94 | Work In Progress | Not Certified |
| 4 | Pilibhit | Bilsanda | Nagariya Tulagiri | 405124 | Simra Mahipat | 94 | 94 | 100 | Har Gar Jal | Not Certified |
| 5 | Pilibhit | Bilsanda | Nagariya Tulagiri | 405125 | Bhoora | 81 | 66 | 81 | Work In Progress | Not Certified |