Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Bulandshahr | JMC - Lakshmi (JV) | 20067101 | Jarara,Meerpur Pahase,Ngla Paharpur WSS | 378.54 | 206.65 | view more | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 37 | 37 | Yes | 0 | NA | No | 17584.00 | 17000.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bulandshahr | Araniya | Jarara | 394221 | Jarara | 384 | 384 | 100 | Har Gar Jal | Not Certified | 
| 2 | Bulandshahr | Araniya | Jarara | 394222 | Paharpur | 89 | 71 | 80 | Work In Progress | Not Certified | 
| 3 | Bulandshahr | Araniya | Nagal | 394223 | Meerpur Pahasu | 129 | 129 | 100 | Har Gar Jal | Certified | 
| 4 | Bulandshahr | Araniya | Nagal | 394224 | Nagal | 164 | 157 | 96 | Work In Progress | Not Certified |