Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Kanpur Dehat | VSA | 20067137 | NAIPLAPUR, RAIPUR | 358.99 | 183.14 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 37 | 37 | Yes | 0 | NA | No | 11254.00 | 10214.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Kanpur Dehat | Sandalpur | Raipur | 421718 | Raipur | 136 | 130 | 96 | Work In Progress | Not Certified |
| 2 | Kanpur Dehat | Sandalpur | Raipur | 421719 | Sukh Rai Pur | 45 | 41 | 91 | Work In Progress | Not Certified |
| 3 | Kanpur Dehat | Sandalpur | Raipur | 421720 | Gangdaspur | 119 | 119 | 100 | Har Gar Jal | Not Certified |
| 4 | Kanpur Dehat | Sandalpur | Naiplapur | 421756 | Naiplapur | 305 | 297 | 97 | Work In Progress | Not Certified |