Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Hardoi | NCC Ltd. | 20067508 | SHAHPUR SHUKUL GOGP JJM | 643.33 | 463.43 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Hardoi | Pihani | GAJUA KHEDA | 412092 | GAJUA KHEDA | 255 | 255 | 100 | Har Gar Jal | Certified | Not Verified |
2 | Hardoi | Pihani | DATYONAPUR | 412112 | KAYAMPUR | 120 | 120 | 100 | Har Gar Jal | Certified | Not Verified |
3 | Hardoi | Pihani | DATYONAPUR | 412113 | GAURIA | 100 | 100 | 100 | Har Gar Jal | Certified | Not Verified |
4 | Hardoi | Pihani | DATYONAPUR | 412114 | DATYONAPUR | 120 | 120 | 100 | Har Gar Jal | Certified | Not Verified |
5 | Hardoi | Pihani | SHAHPUR SHUKLA | 412129 | ANJANA | 15 | 15 | 100 | Har Gar Jal | Certified | Not Verified |
6 | Hardoi | Pihani | SHAHPUR SHUKLA | 412131 | SHAHPUR SHUKLA | 90 | 90 | 100 | Har Gar Jal | Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
6 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 42 | 42 | Yes | 0 | NA | No | 27485.00 | 25963.00 |