Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Pratapgarh | Power Mech Projects Ltd | 20067712 | Bara sarai Gram Panchayat Water Supply | 297.22 | 142.86 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Pratapgarh | Baba Belkharnath Dham | Bara Saray | 430092 | Bara Saray | 228 | 226 | 99 | Work In Progress | Not Certified | Not Verified |
2 | Pratapgarh | Baba Belkharnath Dham | Bara Saray | 430093 | Subhaha | 54 | 54 | 100 | Har Gar Jal | Not Certified | Not Verified |
3 | Pratapgarh | Baba Belkharnath Dham | Bara Saray | 430094 | Pure Kumund Mufrid | 36 | 34 | 94 | Work In Progress | Not Certified | Not Verified |
4 | Pratapgarh | Baba Belkharnath Dham | Bara Saray | 430095 | Pure Mukund Talukdari | 11 | 11 | 100 | Har Gar Jal | Not Certified | Not Verified |
5 | Pratapgarh | Baba Belkharnath Dham | Bara Saray | 430096 | Tiwaripur Khurd | 130 | 130 | 100 | Har Gar Jal | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
5 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 23 | 23 | Yes | 0 | NA | No | 23048.00 | 22673.00 |