Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Mainpuri | NCC Ltd. | 20068727 | KHUSHALPUR + PRAHLADPUR + AMHASAN NAGAR GRAM PANCHAYAT WATER SUPPLY SCHEME | 391.04 | 211.10 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Mainpuri | Barnahal | Khushalpur | 400240 | Kushalpur | 373 | 367 | 98 | Work In Progress | Not Certified | Not Verified |
2 | Mainpuri | Barnahal | Amahasan Nagar | 400248 | Amahasan Nagar | 249 | 249 | 100 | Har Gar Jal | Not Certified | Not Verified |
3 | Mainpuri | Barnahal | Prahladpur | 400283 | Prahladpur | 307 | 302 | 98 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 37 | 37 | Yes | 0 | NA | No | 18769.00 | 18420.00 |