Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Kushi Nagar | NCC Ltd. | 20072495 | AHLADPUR | 285.39 | 129.02 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Kushi Nagar | Tamkuhi Raj | Ahladpur | 458715 | Ahladpur | 604 | 604 | 100 | Har Gar Jal | Not Certified | Not Verified |
2 | Kushi Nagar | Tamkuhi Raj | Ahladpur | 458716 | Bishunpura | 56 | 56 | 100 | Har Gar Jal | Not Certified | Not Verified |
3 | Kushi Nagar | Tamkuhi Raj | Ahladpur | 458717 | Matloob Chapar | 85 | 85 | 100 | Har Gar Jal | Not Certified | Not Verified |
4 | Kushi Nagar | Tamkuhi Raj | Gauri Narottam | 458800 | Gadai Patti | 143 | 143 | 100 | Har Gar Jal | Certified | Not Verified |
5 | Kushi Nagar | Tamkuhi Raj | MOGALPURA | 702917 | GADARI | 20 | 15 | 75 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
5 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 13 | 13 | Yes | 0 | NA | No | 10992.00 | 8195.00 |