Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Shahjahanpur | NCC Ltd. | 20073500 | DAHAR & KHANDHAR WSS | 561.13 | 280.38 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Shahjahanpur | Jalalabad | Khandhar | 407668 | Khandhar | 783 | 778 | 99 | Work In Progress | Not Certified | Not Verified |
2 | Shahjahanpur | Jalalabad | Dahar | 407672 | Dahar | 234 | 234 | 100 | Har Gar Jal | Certified | Not Verified |
3 | Shahjahanpur | Jalalabad | Dahar | 407673 | Basua Mai | 99 | 99 | 100 | Har Gar Jal | Certified | Not Verified |
4 | Shahjahanpur | Jalalabad | Dahar | 407674 | Kateli | 108 | 108 | 100 | Har Gar Jal | Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 35 | 35 | Yes | 0 | NA | No | 23044.00 | 23000.00 |