Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | HFCL- JWIL (JV) | 20075421 | JAHNI W/S SCHEME (HFCL) | 323.79 | 109.61 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 16 | 16 | NA | 0 | NA | No | 9564.00 | 100.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Jakhania | Jahni | 471507 | Jahni | 522 | 472 | 90 | Work In Progress | Not Certified |
| 2 | Ghazipur | Jakhania | Jahni | 471508 | Araji Mafi Haridyal Yati | 12 | 11 | 92 | Work In Progress | Not Certified |