Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | VSA | 20076017 | MAHUA KHURD GP WSS | 223.81 | 36.73 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 16 | 16 | Yes | 0 | NA | No | 10891.00 | 10891.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | Khuniyaon | Mahua Khurd | 448353 | Mahua Khurd | 154 | 154 | 100 | Har Gar Jal | Not Certified |
| 2 | Siddharth Nagar | Khuniyaon | Mahua Khurd | 448354 | Ramwapur Pathak | 113 | 105 | 93 | Work In Progress | Not Certified |
| 3 | Siddharth Nagar | Khuniyaon | Mahua Khurd | 448355 | Madanpur Bujurg | 2 | 1 | 50 | Work In Progress | Not Certified |