Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Ayodhya | VSA | 20076227 | LUFTABAD BACHHAULI | 1006.95 | 758.08 | Verified | Verified | view more |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Ayodhya | Bikapur | LUFTABAD BACHHAULI | 437162 | SURA SARAI | 31 | 31 | 100 | Har Gar Jal | Not Certified | Not Verified |
2 | Ayodhya | Bikapur | LUFTABAD BACHHAULI | 437170 | Luftabad Bachhauli | 600 | 600 | 100 | Har Gar Jal | Not Certified | Not Verified |
3 | Ayodhya | Bikapur | CHANDPUR | 437171 | CHANDPUR | 215 | 215 | 100 | Har Gar Jal | Not Certified | Not Verified |
4 | Ayodhya | Bikapur | JALALPUR MAFI | 437172 | RAHET | 78 | 78 | 100 | Har Gar Jal | Not Certified | Not Verified |
5 | Ayodhya | Bikapur | JALALPUR MAFI | 437184 | Jalalpur Mafi | 302 | 302 | 100 | Har Gar Jal | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
5 | 2 | 2 | 2 | 2 | 1 | 1 | 1 | 42 | 42 | Yes | 0 | NA | No | 55844.00 | 40238.00 |