Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Siddharth Nagar | JAKSON - VISHVARAJ (JV) | 20076373 | BHELAUJI BUZURG GP WSS | 227.95 | 92.32 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Siddharth Nagar | Lotan Bazar | Bhelauji Buzurg | 446992 | Bhelauji Buzurg | 246 | 118 | 48 | Work In Progress | Not Certified | Not Verified |
2 | Siddharth Nagar | Lotan Bazar | Bhelauji Buzurg | 446993 | Bhelauji Khurd | 13 | 4 | 31 | Work In Progress | Not Certified | Not Verified |
3 | Siddharth Nagar | Lotan Bazar | Bhelauji Buzurg | 446994 | Jhuganwa | 4 | 2 | 50 | Work In Progress | Not Certified | Not Verified |
4 | Siddharth Nagar | Lotan Bazar | Bhelauji Buzurg | 446995 | Khajuriya | 96 | 77 | 80 | Work In Progress | Not Certified | Not Verified |
5 | Siddharth Nagar | Lotan Bazar | Bhelauji Buzurg | 446996 | Mhua Mafi | 132 | 1 | 1 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
5 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 20 | 20 | Yes | 0 | NA | No | 5539.00 | 7500.00 |