Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | JAKSON - VISHVARAJ (JV) | 20076458 | BARGADWA AND KARAMDEEH JAMUAR GP WSS | 335.60 | 163.08 | view more | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 20 | 20 | Yes | 0 | NA | No | 15999.00 | 15900.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | Khesraha | Bargadwa | 447628 | Bargadwa | 110 | 109 | 99 | Work In Progress | Not Certified | 
| 2 | Siddharth Nagar | Khesraha | Bargadwa | 447629 | Bardand | 37 | 36 | 97 | Work In Progress | Not Certified | 
| 3 | Siddharth Nagar | Khesraha | Bargadwa | 447630 | Batulaha Bhatauli | 55 | 36 | 65 | Work In Progress | Not Certified | 
| 4 | Siddharth Nagar | Khesraha | Bargadwa | 447632 | Majharia Khurd | 28 | 28 | 100 | Har Gar Jal | Not Certified | 
| 5 | Siddharth Nagar | Khesraha | Karmdih Jamuwar | 447634 | Wazirabad | 86 | 85 | 99 | Work In Progress | Not Certified | 
| 6 | Siddharth Nagar | Khesraha | Karmdih Jamuwar | 447635 | Karamdeeh Jamuar | 75 | 74 | 99 | Work In Progress | Not Certified |