Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Siddharth Nagar | JAKSON - VISHVARAJ (JV) | 20076653 | KUSH BHAWWANA GP WSS | 211.67 | 108.25 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Siddharth Nagar | Naugarh | Kush Bhauna | 446668 | Kush Bhawwana | 214 | 142 | 66 | Work In Progress | Not Certified | Not Verified |
2 | Siddharth Nagar | Naugarh | Kush Bhauna | 446669 | Deopur Bando Basti | 39 | 30 | 77 | Work In Progress | Not Certified | Not Verified |
3 | Siddharth Nagar | Naugarh | Kush Bhauna | 446670 | Nauwa Dani | 12 | 1 | 8 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 16 | 16 | Yes | 0 | NA | No | 9612.00 | 9600.00 |