| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | JAKSON - VISHVARAJ (JV) | 20076671 | PACH MOHANI GP WSS | 206.94 | 108.76 | view more | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 13 | 13 | Yes | 0 | NA | No | 10836.00 | 10700.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | Itwa | Pach Mohani | 448012 | MUDILA | 48 | 0 | 0 | Work In Progress | Not Certified | 
| 2 | Siddharth Nagar | Itwa | Pach Mohani | 448045 | Pach Mohni | 106 | 105 | 99 | Work In Progress | Not Certified | 
| 3 | Siddharth Nagar | Itwa | Pach Mohani | 448047 | Bhelauha | 20 | 19 | 95 | Work In Progress | Not Certified | 
| 4 | Siddharth Nagar | Itwa | Pach Mohani | 448102 | Semri Nankar | 105 | 28 | 27 | Work In Progress | Not Certified |