Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Muzaffarnagar | NKG-PRIMUS (JV) | 20076946 | NAWALA MV WSS | 559.52 | 406.57 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 0 | NA | 63 | NA | No | 23761.00 | 12000.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Muzaffarnagar | Khatauli | Nawala | 385485 | Nawala | 1883 | 1795 | 95 | Work In Progress | Not Certified |
| 2 | Muzaffarnagar | Khatauli | Nawala | 385486 | Akbarpur | 9 | 1 | 11 | Work In Progress | Not Certified |
| 3 | Muzaffarnagar | Khatauli | Nawala | 385487 | Munawwarpur Khurd | 4 | 2 | 50 | Work In Progress | Not Certified |
| 4 | Muzaffarnagar | Khatauli | Nawala | 657412 | Habibpur | 2 | 2 | 100 | Har Gar Jal | Not Certified |
| 5 | Muzaffarnagar | Khatauli | Nawala | 657417 | Rustampoor | 2 | 2 | 100 | Har Gar Jal | Not Certified |