Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Kanpur Dehat | GVPR | 20077297 | Laruapur & Nandpur | 427.31 | 340.03 | view more | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 37 | 37 | Yes | 0 | NA | No | 15671.00 | 15271.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Kanpur Dehat | Derapur | Laruwapur | 421289 | Jahli | 121 | 121 | 100 | Har Gar Jal | Not Certified | 
| 2 | Kanpur Dehat | Derapur | Laruwapur | 421290 | Laruwapur | 283 | 283 | 100 | Har Gar Jal | Not Certified | 
| 3 | Kanpur Dehat | Derapur | Nandpur | 421305 | Kaira Mau | 110 | 110 | 100 | Har Gar Jal | Not Certified | 
| 4 | Kanpur Dehat | Derapur | Nandpur | 421306 | Nandpur | 154 | 154 | 100 | Har Gar Jal | Not Certified |