Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Prayagraj | Larsen & Toubro Ltd | 20077760 | KANAUJA KHURD_KANAUJA KLA_JAFERPUR URF BABUGANJ WATER SUPPLY SCHEME | 342.93 | 157.99 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Prayagraj | SAHSON | KANAUJA KHURD | 432308 | KANAUJA KHURD | 226 | 220 | 97 | Work In Progress | Not Certified | Not Verified |
2 | Prayagraj | SAHSON | KANAUJA KLA | 432309 | KANAUJA KALA | 171 | 148 | 87 | Work In Progress | Not Certified | Not Verified |
3 | Prayagraj | Phulpur | Jaferpur Urf Babuganj | 432336 | Jaferpur Urf Babuganj | 337 | 312 | 93 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 35 | 35 | Yes | 0 | NA | No | 18632.00 | 18600.00 |