Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Sultanpur | Vindhya-GAJA (JV) | 20078202 | DHESARUA & MEERRDASPUR WSS | 673.35 | 292.04 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 2 | 2 | 2 | 2 | 1 | 1 | 0 | 43 | 43 | Yes | 0 | NA | No | 36268.00 | 36543.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sultanpur | Kurebhar | Dhesarua | 440145 | Dhesarua | 642 | 624 | 97 | Work In Progress | Not Certified | 
| 2 | Sultanpur | Kurebhar | Meerdaspur | 440148 | Churkuna Asharafpur | 102 | 96 | 94 | Work In Progress | Not Certified | 
| 3 | Sultanpur | Kurebhar | Meerdaspur | 440149 | Mirdaspur | 155 | 146 | 94 | Work In Progress | Not Certified |