S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Sultanpur Vindhya-GAJA (JV) 20078208 MALIKPUR & CHANDPUR SAIDO PATTI WSS 476.22 169.62 Not Integrated

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
3 1 1 1 1 1 1 0 27 27 NA 0 NA No 35879.00 35879.00

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Sultanpur Kurebhar Malikpur 440167 Malik Pur 224 214 96 Work In Progress Not Certified
2 Sultanpur Kurebhar Malikpur 440168 Balaramau 76 70 92 Work In Progress Not Certified
3 Sultanpur Kurebhar Chandpur Saido Patti 440183 Chandpur Saido Patti 310 297 96 Work In Progress Not Certified