Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Kushi Nagar | NCC Ltd. | 20078851 | SARISWA | 624.35 | 261.56 | Verified | Not Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Kushi Nagar | Dudhahi | Khiriya | 458873 | Khiriya | 268 | 211 | 79 | Work In Progress | Not Certified | Not Verified |
2 | Kushi Nagar | Dudhahi | Sariswa | 458875 | Sariswa | 475 | 475 | 100 | Har Gar Jal | Certified | Not Verified |
3 | Kushi Nagar | Dudhahi | Korya | 458876 | Korya | 411 | 411 | 100 | Har Gar Jal | Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 44 | 44 | Yes | 0 | NA | No | 22000.00 | 22000.00 |