Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Mainpuri | NCC Ltd. | 20078944 | HATPAU + NAVADA + GADAIPURA GRAM PANCHAYAT WATER SUPPLY SCHEME | 1203.36 | 660.26 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Mainpuri | Jagir | GADAIPURA | 400678 | Gadaipura | 120 | 119 | 99 | Work In Progress | Not Certified | Not Verified |
2 | Mainpuri | Jagir | GADAIPURA | 400679 | Madhupuri | 82 | 82 | 100 | Har Gar Jal | Certified | Not Verified |
3 | Mainpuri | Jagir | Hatpau | 400693 | Hatpau | 1181 | 1142 | 97 | Work In Progress | Not Certified | Not Verified |
4 | Mainpuri | Jagir | Navada | 400695 | Navada | 261 | 255 | 98 | Work In Progress | Not Certified | Not Verified |
5 | Mainpuri | Jagir | GADAIPURA | 677458 | Chauhanpur | 85 | 85 | 100 | Har Gar Jal | Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
5 | 4 | 4 | 4 | 4 | 4 | 4 | 1 | 82 | 82 | Yes | 0 | NA | No | 66701.00 | 66401.00 |