Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Muzaffarnagar | JMC - Lakshmi (JV) | 20079788 | NAGLA KABIR & KHERTAULI MV WSS | 212.85 | 72.00 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 0 | NA | 25 | NA | No | 8005.00 | 2012.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Muzaffarnagar | Jansath | Nagla Kabir | 385354 | Nagla Kabir | 299 | 148 | 49 | Work In Progress | Not Certified |
| 2 | Muzaffarnagar | Jansath | Nagla Kabir | 385355 | Khertauli | 27 | 4 | 15 | Work In Progress | Not Certified |