Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Kushi Nagar | NCC Ltd. | 20081802 | DEOTAHA WALI | 655.76 | 342.66 | Verified | Not Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Kushi Nagar | Nebua Naurangiya | Bali | 457587 | Bali | 141 | 141 | 100 | Har Gar Jal | Not Certified | Not Verified |
2 | Kushi Nagar | Nebua Naurangiya | Bali | 457588 | Deotaha | 873 | 785 | 90 | Work In Progress | Not Certified | Not Verified |
3 | Kushi Nagar | Nebua Naurangiya | Baluahi | 457589 | Baluahi | 311 | 311 | 100 | Har Gar Jal | Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 51 | 51 | Yes | 0 | NA | No | 30140.00 | 30140.00 |