Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Kushi Nagar | NCC Ltd. | 20081808 | DURGWALIYA | 364.81 | 220.28 | Verified | Not Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Kushi Nagar | Padrauna | Jigana | 457940 | Jigana | 234 | 234 | 100 | Har Gar Jal | Certified | Not Verified |
2 | Kushi Nagar | Padrauna | Jigana | 457941 | Jigani | 55 | 55 | 100 | Har Gar Jal | Certified | Not Verified |
3 | Kushi Nagar | Padrauna | Durgawaliya | 457942 | Durgwalia | 443 | 443 | 100 | Har Gar Jal | Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 27 | 37 | Yes | 0 | NA | No | 12917.00 | 12917.00 |