Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Sultanpur | Vindhya-GAJA (JV) | 20084506 | DAULATPUR, GAURA BIBIPUR, PANDELA WSS | 524.54 | 333.42 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 37 | 37 | Yes | 0 | NA | No | 33654.00 | 31575.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sultanpur | Kadipur | Gaura Bibipur | 441324 | Gaura Bibipur | 244 | 220 | 90 | Work In Progress | Not Certified | 
| 2 | Sultanpur | Kadipur | Pandela | 441325 | Pandela | 227 | 218 | 96 | Work In Progress | Not Certified | 
| 3 | Sultanpur | Kadipur | Daulatpur | 441326 | Daulatpur | 221 | 221 | 100 | Har Gar Jal | Not Certified | 
| 4 | Sultanpur | Kadipur | Pandela | 441327 | Chatur Khirjabad | 72 | 63 | 88 | Work In Progress | Not Certified |