Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Basti | JAKSON - VISHVARAJ (JV) | 20085057 | KISUNPUR GP wss | 256.89 | 144.76 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Basti | Gaur | Kisunpur | 449417 | Kisunpur | 123 | 110 | 89 | Work In Progress | Not Certified | Not Verified |
2 | Basti | Gaur | Kisunpur | 449418 | Mehdiya Khadak Bahadur Sahi | 112 | 90 | 80 | Work In Progress | Not Certified | Not Verified |
3 | Basti | Gaur | Kisunpur | 449419 | Tituharai | 57 | 39 | 68 | Work In Progress | Not Certified | Not Verified |
4 | Basti | Gaur | Kisunpur | 449420 | Pachmohni | 19 | 8 | 42 | Work In Progress | Not Certified | Not Verified |
5 | Basti | Gaur | Kisunpur | 680594 | Reuwababu | 76 | 75 | 99 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
5 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 16 | 16 | Yes | 0 | NA | No | 11986.00 | 11000.00 |