Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Sant Kabeer Nagar | JAKSON - VISHVARAJ (JV) | 20085438 | SUKRAULI & OJHA PATTI GOV WSS | 331.74 | 163.06 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Sant Kabeer Nagar | Nathnagar | Ojha Patti | 452827 | Harsaio | 105 | 105 | 100 | Har Gar Jal | Not Certified | Not Verified |
2 | Sant Kabeer Nagar | Nathnagar | Ojha Patti | 452829 | Ojha Patti | 110 | 106 | 96 | Work In Progress | Not Certified | Not Verified |
3 | Sant Kabeer Nagar | Nathnagar | Ojha Patti | 452830 | Andhra Patti | 11 | 8 | 73 | Work In Progress | Not Certified | Not Verified |
4 | Sant Kabeer Nagar | Nathnagar | Sukruli | 452832 | Sukrauli | 138 | 127 | 92 | Work In Progress | Not Certified | Not Verified |
5 | Sant Kabeer Nagar | Nathnagar | Sukruli | 452833 | Padum Patti | 93 | 88 | 95 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
5 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 23 | 23 | Yes | 0 | NA | No | 17779.00 | 14993.00 |