Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Raebareli | U.P.Jal Nigam | 20085473 | KAMALPUR G.O.V. REORGANIZATION WATER SUPPLY SCHEME (SOLAR) | 953.00 | 145.57 | Not Integrated |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Raebareli | Rohiniyan | Kamalpur | 417513 | Kamalpur | 242 | 200 | 83 | Work In Progress | Not Certified |
| 2 | Raebareli | Rohiniyan | Parsipur | 417516 | Parsipur | 122 | 90 | 74 | Work In Progress | Not Certified |
| 3 | Raebareli | Rohiniyan | Parsipur | 417517 | Samasapur Patauna | 115 | 115 | 100 | Har Gar Jal | Not Certified |
| 4 | Raebareli | Rohiniyan | Parsipur | 417518 | Sarakpur | 198 | 25 | 13 | Work In Progress | Not Certified |
| 5 | Raebareli | Rohiniyan | Gagehara Gulal Ganj | 417519 | Gagehara Gulal Ganj | 439 | 439 | 100 | Har Gar Jal | Not Certified |
| 6 | Raebareli | Rohiniyan | Gagehara Gulal Ganj | 417520 | Hajaribag | 59 | 57 | 97 | Work In Progress | Not Certified |
| 7 | Raebareli | Rohiniyan | Gagehara Gulal Ganj | 417521 | Raghunathpur Labedawa | 66 | 16 | 24 | Work In Progress | Not Certified |
| 8 | Raebareli | Rohiniyan | Gagehara Gulal Ganj | 417522 | RAGHUNATHPUR PATERWA | 76 | 36 | 47 | Work In Progress | Not Certified |
| 9 | Raebareli | Rohiniyan | Dhaurhara | 417528 | Masaudabad | 88 | 86 | 98 | Work In Progress | Not Certified |
| 10 | Raebareli | Rohiniyan | Dhaurhara | 417538 | Dhaurhara | 140 | 138 | 99 | Work In Progress | Not Certified |