Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Lakhimpur Kheri | NCC Ltd. | 20085515 | ALLIPUR JJM SCHEME | 223.70 | 97.67 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 20 | 20 | Yes | 0 | NA | No | 10619.00 | 4100.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Lakhimpur Kheri | Pasgawan | Allipur | 408751 | Allipur | 336 | 197 | 59 | Work In Progress | Not Certified |
| 2 | Lakhimpur Kheri | Pasgawan | Allipur | 408752 | Mastipur | 172 | 29 | 17 | Work In Progress | Not Certified |