Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Prayagraj | Larsen & Toubro Ltd | 20085546 | KATIYARI URF CHAKIYA_RATAURA WATER SUPPLY SCHEME | 247.04 | 135.25 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Prayagraj | Bahadurpur | Katiyari Urf Chakiya | 432455 | Katiyari Urf Chakiya | 221 | 220 | 100 | Work In Progress | Not Certified | Not Verified |
2 | Prayagraj | Bahadurpur | Rataura | 432456 | Rataura | 213 | 213 | 100 | Har Gar Jal | Not Certified | Not Verified |
3 | Prayagraj | Bahadurpur | Katiyari Urf Chakiya | 432457 | Chak Kutubuddin | 35 | 35 | 100 | Har Gar Jal | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 21 | 21 | Yes | 0 | NA | No | 15904.00 | 15900.00 |