| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | M/s Sudhakara Infratech Pvt. Ltd | 20086090 | PATTI water supply scheme | 230.71 | 119.82 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 16 | 16 | Yes | 0 | NA | No | 11982.00 | 11936.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | Meh Nagar | Patti | 464689 | Raipur | 105 | 66 | 63 | Work In Progress | Not Certified |
| 2 | Azamgarh | Meh Nagar | Patti | 464690 | Patti | 107 | 104 | 97 | Work In Progress | Not Certified |
| 3 | Azamgarh | Meh Nagar | Patti | 464691 | Baijanathpur | 42 | 42 | 100 | Har Gar Jal | Not Certified |