Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Lakhimpur Kheri | Vindhya-GAJA (JV) | 20086153 | Saidipur,Devria JJM SCHEME | 486.46 | 274.56 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 27 | 27 | Yes | 0 | NA | No | 26564.00 | 26460.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Lakhimpur Kheri | Phoolbehar | Devria | 409174 | Devria | 637 | 637 | 100 | Har Gar Jal | Not Certified |
| 2 | Lakhimpur Kheri | Phoolbehar | Saidipur | 409176 | Saidipur | 287 | 287 | 100 | Har Gar Jal | Not Certified |