Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | VSA | 20086611 | HATA,SALEMPUR & DAUDPUR REORGANISATION W/S SCHEME (VSA) | 406.15 | 108.87 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 7 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 0 | NA | 15 | NA | No | 20363.00 | 0.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Mohammadabad | Daud Pur | 473556 | Daud Pur | 166 | 155 | 93 | Work In Progress | Not Certified |
| 2 | Ghazipur | Mohammadabad | Daud Pur | 473557 | Chak Manawar | 17 | 11 | 65 | Work In Progress | Not Certified |
| 3 | Ghazipur | Mohammadabad | Salem Pur | 473634 | Salem Pur | 279 | 255 | 91 | Work In Progress | Not Certified |
| 4 | Ghazipur | Mohammadabad | Salem Pur | 473637 | Chak Lala Bad Faros | 9 | 6 | 67 | Work In Progress | Not Certified |
| 5 | Ghazipur | Mohammadabad | Hata | 473654 | Hata | 303 | 277 | 91 | Work In Progress | Not Certified |
| 6 | Ghazipur | Mohammadabad | Daud Pur | 473655 | CHAK KHAIRULLAH URF LACHIPAH | 80 | 62 | 78 | Work In Progress | Not Certified |
| 7 | Ghazipur | Mohammadabad | Hata | 473656 | Nashir Pur Kala | 33 | 1 | 3 | Work In Progress | Not Certified |