Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Sant Kabeer Nagar | JAKSON - VISHVARAJ (JV) | 20086697 | BAHRA DANDI GP WSS | 265.61 | 130.67 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 20 | 20 | Yes | 0 | NA | No | 12988.00 | 11843.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sant Kabeer Nagar | Haisar Bazar | Bahra Dandi | 452984 | Bahra Dandi | 291 | 289 | 99 | Work In Progress | Not Certified | 
| 2 | Sant Kabeer Nagar | Haisar Bazar | Bahra Dandi | 452985 | Karanpur | 21 | 20 | 95 | Work In Progress | Not Certified | 
| 3 | Sant Kabeer Nagar | Haisar Bazar | Bahra Dandi | 452986 | Kanchanpur | 63 | 63 | 100 | Har Gar Jal | Not Certified | 
| 4 | Sant Kabeer Nagar | Haisar Bazar | Bahra Dandi | 656823 | Sear Jot | 2 | 1 | 50 | Work In Progress | Not Certified |