Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Sant Kabeer Nagar | JAKSON - VISHVARAJ (JV) | 20086895 | Pipra Doman & Muradeeha Khurd GP WSS | 300.80 | 121.47 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 23 | 23 | No | 0 | NA | No | 9299.00 | 7839.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sant Kabeer Nagar | Semariyawan | Muradeeha Khurd | 452388 | Muradeeha Khurd | 309 | 309 | 100 | Har Gar Jal | Not Certified |
| 2 | Sant Kabeer Nagar | Semariyawan | Pipra Doman | 452389 | Pipra Doman | 104 | 93 | 89 | Work In Progress | Not Certified |