Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | GAJA - SGIPL (JV) | 20087070 | GANGWAL & MAKBOLPUR (RAMNAGAR) WATER SUPPLY SCHEME | 424.74 | 130.33 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 0 | 1 | 0 | 0 | 27 | 27 | NA | 0 | NA | No | 26745.00 | 26745.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | Tarwan | Gangwal | 464593 | Gangwal | 115 | 72 | 63 | Work In Progress | Not Certified | 
| 2 | Azamgarh | Tarwan | Gangwal | 464594 | Dhajawal | 88 | 9 | 10 | Work In Progress | Not Certified | 
| 3 | Azamgarh | Tarwan | Makbolpur (ramnagar) | 464595 | Makbolpur (ramnagar | 242 | 152 | 63 | Work In Progress | Not Certified |